Fonterra Fibre Cabling Upgrade

Home / Fonterra Fibre Cabling Upgrade
Edit Template

Aotea Communications — a division of Aotea Electric Invercargill, are completing a full site fiber backbone upgrade at the Fonterra Edendale site.

This project consists of installation of 10,000m of 12 core fiber, 2200 fiber splices, installation of 56 server cabinets and install of cat6a data cable.

This 9000-hour project needs to be well organised to deal with the challenging nature of a milk processing plant and engaging with over 50 different departments to make sure the projects keeps moving forward and get delivered on time.